1.
|
PRE-CONSTRUCTION
MEETING:
|
|
|
|
|
|
|
|
Prior
to commencement of construction, the pad contractor is required
to meet with the McCarthy Building Co. Site Superintendent to review
project policies and procedures, and to establish a staging area
agreement. The following documents must be furnished prior
to mobilizing on-site:
|
|
|
|
a)
|
Submit
a Certificate of Insurance to Vestar Development Company with a
copy to McCarthy Building Co. naming the following entities as additionally
insured:
|
|
|
|
|
i) Arizona State
Land Department
|
|
|
|
|
ii) Bank of America, NA,
as Agent
|
|
|
|
|
iii) Vestar DRM-OPCO, L.L.C.
|
|
|
|
|
iv) Vestar Arizona XXXIII, L.L.C.
|
|
|
|
|
v) DLJ Real Estate Capital
Partners II, L.P.
|
|
|
|
|
vi) DLJ Exchange Capital Partners
II, L.P.
|
|
|
|
|
vii) McCarthy Building Company
|
|
|
|
b)
|
Provide
a 24-hour contact list, which should include all Subcontractors
onsite.
|
|
|
|
c)
|
Provide
a copy of pad contractor's State of Arizona general contractor's
license.
|
|
|
|
d)
|
Provide
an 8 1/2" x 11" Staging Area Plan approved
by McCarthy Building Co. as indicated by a McCarthy Building Co.
representative signature on said plan. |
|
|
|
|
|
|
|
|
Construction
may not commence without the pad contractor having an executed letter
of intent or construction contract with Vestar Development Company.
|
|
|
|
|
|
|
|
2.
|
COORDINATION
AND COOPERATION:
|
|
|
|
|
|
|
|
|
The
pad contractor shall not interfere or impede site or surrounding
building work. In the event pad contractor willfully violates
requirements of these Rules and Regulations, McCarthy Building Co.
may order the pad contractor to remove its equipment and its employees
from the Project Site.
|
|
|
|
|
|
|
|
3.
|
JOB
CONDUCT GUIDELINES:
|
|
|
|
|
|
|
|
|
Workers
shall be confined to approved staging areas and are required to
maintain good discipline. Violation of the Job Conduct Guidelines
or violation of Basic Safety Rules and Regulations as required by
O.S.H.A. and entitles McCarthy Building Co. to cause violating individual
and/or pad contractor to being removed from the site. Any
injury or accident must be immediately reported, in writing, to
McCarthy Building Co.'s Project Manager or Site Superintendent.
|
|
|
|
|
|
|
|
|
a)
|
Head
Protection
|
|
|
|
|
 |
Hard
hats must be worn at all times. NO EXCEPTIONS.
|
|
|
|
|
b)
|
First
Aid
|
|
|
|
|
 |
Every
pad contractor is expected to provide adequate first aid and
safety kits to care for any injury of their employees.
|
|
|
|
|
c)
|
Fire
Control
|
|
|
|
|
 |
No
open fires, fire barrels or hot boxes.
|
|
|
|
|
|
 |
Fire
extinguishers are required in:
|
|
|
|
|
|
|
Trailer/office
‚ minimum 10 lb. ABC
|
|
|
|
|
|
Equipment
‚ minimum 5 lb. ABC
|
|
|
|
|
|
Fire
Watch ‚ minimum 20 lb. ABC
|
|
|
|
|
 |
Extinguishers
must be on lifts and scaffold, not on the floor.
|
|
|
|
|
|
 |
Combustible
materials storage is not permitted on site.
|
|
|
|
|
|
 |
Construction
trash may not accumulate. The grounds and parking area
are to be kept clean at all times.
|
|
|
|
|
d)
|
Foot
Protection
|
|
|
|
|
 |
Work
boots are required. Loafers, tennis shoes, or soft soled
shoes are not allowed.
|
|
|
|
|
e)
|
Ladders
|
|
|
|
|
 |
No
metal ladders are allowed on site. Damaged ladders must
be immediately removed from this project.
|
|
|
|
|
f)
|
Scaffolding
|
|
|
|
|
 |
Full
handrails, mid-rails, toeboards, full decking are required
on all scaffolding regardless of height. Access ladders
must either be built in or attached.
|
|
|
|
|
g)
|
Work
Clothing
|
|
|
|
|
 |
All
shirts must have a minimum of four (4)-inch sleeve length
over shoulders and must be worn at all times. No shorts,
cut-offs, tank tops, etc.
|
|
|
|
|
h)
|
Electrical
|
|
|
|
|
 |
GFI
protection is required on all electrical systems.
|
|
|
|
|
I)
|
Signage
|
|
|
|
|
 |
Signage
must be posted for public safety and/or general warning.
|
|
|
|
|
|
 |
All
marketing signage must be submitted to Vestar Development
Company for approval. Send all requests in writing to
Robert Kerwin, Vestar Development Company, 2425 E. Camelback
Road, Suite 750, Phoenix, Arizona 85016
|
|
|
|
|
|
|
|
|
|
Safety
issues include, but are not limited to, the above guidelines.
|
|
|
|
|
|
|
|
4.
|
PAD
CONTRACTOR'S OFFICES AND BUILDINGS:
|
|
|
|
|
|
|
|
|
Arrangements
for the location of the pad contractor's staging area, project office
trailer, sheds, roll-off dumpster, waste containers, portable toilets,
etc. shall be made with the Site Superintendent during your pre-construction
meeting. All staging areas must be secured with 6' high chain-link
fencing. NO EXCEPTIONS! You may be asked to relocate
your field operations during the course of construction. This
relocation must be completed within ten (10) days of notification
by McCarthy Building Co. All costs associated with a move
are the pad contractor's responsibility.
|
|
|
|
|
|
|
|
5.
|
PROJECT
WORK HOURS:
|
|
|
|
|
|
|
|
|
This
site is accessible from 5:00am to 5:00pm seven (7) days per week.
Any variations to these hours will be posted by McCarthy Building
Co. Special consideration will be given for off-hour access
on an individual, as needed, basis.
|
|
|
|
|
|
|
|
6.
|
JOB
SITE STORAGE:
|
|
|
|
|
|
|
|
|
It
will be determined during your pre-construction meeting with the
Project Manager or Site Superintendent if a staging area for materials,
tools and equipment is available on site. Job site storage
is limited and it may be necessary to arrange for off site storage.
If a site location is available, it will be on a temporary basis
only. You may be asked to relocated to accommodate base building
and/or site work.
|
|
|
|
|
|
|
|
|
Any
damage or losses resulting from storage of materials, tools and
equipment shall be remedied at the cost of the pad contractor.
The pad contractor is responsible for erection, dismantling, maintenance,
utilities, fencing, telephone, security, etc. that it deems necessary
in setting up its offices, sheds and storage areas.
|
|
|
|
|
|
|
|
|
Materials
and Equipment temporarily stored at the Premises shall be located
so as not to interfere with the work of any other pad contractor
or McCarthy Building Co.'s subcontractors. Storage areas are
to be maintained in a clean, orderly manner and to McCarthy Building
Co.'s satisfaction.
|
|
|
|
|
|
|
|
7.
|
DRINKING
WATER:
|
|
|
|
|
|
|
|
|
Each
pad contractor is to provide ice and portable water at the job site
for use by pad contractor's field workmen.
|
|
|
|
|
|
|
|
8.
|
TEMPORARY
TELEPHONE:
|
|
|
|
|
|
|
|
|
Each
pad contractor is responsible for providing a required telephone
service for performing the work under his or her respective contract.
|
|
|
|
|
|
|
|
9.
|
TEMPORARY
POWER AND LIGHTING:
|
|
|
|
|
|
|
|
|
Each
pad contractor is responsible for providing temporary power as required
for its job completion. The Site Superintendent will advise
of availability and location.
|
|
|
|
|
|
|
|
10.
|
MISCELLANEOUS
TEMPORARY FACILITIES:
|
|
|
|
|
|
|
|
|
Each
pad contractor, at his own expense, shall provide any other temporary
facilities and/or requirements the trade contractors believe to
be required by his work.
|
|
|
|
|
|
|
|
11.
|
TRAFFIC
CONTROL:
|
|
|
|
|
|
|
|
|
The
pad contractor is responsible for any traffic control and barricades
necessary to perform their work. The project speed limit is
10 mph.
|
|
|
|
|
|
|
|
12.
|
ACCESS
AND MATERIAL DELIVERY:
|
|
|
|
|
|
|
|
|
An
access route to your space will be through a site gate location
to be selected by McCarthy Building Co. All construction personnel
and deliveries are required to use this entry. It is the responsibility
of the pad contractor to ensure that all personnel and vendors making
deliveries to the job site are aware of the job site location and
access route. McCarthy Building Co. will not direct or accept
your deliveries. You will be notified should project conditions
necessitate an access route change.
|
|
|
|
|
|
|
|
|
Deliveries
to the site shall be controlled so that materials are not stored
for excessive periods before erection and incorporation into the
structure or structures.
|
|
|
|
|
|
|
|
13.
|
PARKING:
|
|
|
|
|
|
|
|
|
Pad
contractors and their employees are restricted to the staging areas
designated by the Lease Exhibit (or in the absence of a Lease Exhibit,
by McCarthy Building Co.) and are subject to change. Construction
vehicles parked other than in designated areas may be subject to
towing without prior notification. Towing and retrieving costs
are at the vehicle owner's expense.
|
|
|
|
|
|
|
|
|
Parking
in driveways, fire lanes and established loading zones is strictly
prohibited. Delivery vehicles must be completely unloaded
at curbside and then moved out. Unattended vehicles in loading
zones will be tagged or towed at the vehicle owner's expense.
|
|
|
|
|
|
|
|
14.
|
PROTECTION
OF EXISTING UTILITIES:
|
|
|
|
|
|
|
|
|
The
pad contractor is responsible for verifying the exact location of
all existing utilities. The contractor shall protect utilities
left in service including construction temporary power and telephone
lines at all times. Any damage to utility lines caused by
the pad contractor operations shall be reported promptly to the
owning utility company. The utility company shall make repairs
at the pad contractor's expense.
|
|
|
|
|
|
|
|
15.
|
MISCELLANEOUS
PROTECTION:
|
|
|
|
|
|
|
|
|
The
pad contractors are responsible for protecting property, personnel
and the work of other pad contractors in carrying out their work.
The pad contractor is responsible for all cost of patching, repairs
and replacement for work damaged by their work forces. The
pad contractor shall take all reasonable precautions to protect
their work from damage by other pad contractors including providing
and maintaining protection and barricading of their work area.
This includes, but is not limited to, any open trenches, pits and
shafts, holes in floor or walls, and similar potentially hazardous
areas. All pad contractors shall fence their respective work
and staging area.
|
|
|
|
|
|
|
|
16.
|
CLEAN-UP/TRASH:
|
|
|
|
|
|
|
|
|
Clean
up shall include removal and legal disposal of all debris from the
site. The pad contractor shall remove empty carton, crates
and other combustible refuse from the premises daily. Dirt
or rubbish is not allowed to accumulate so it becomes detrimental
to employees or to the work of the various trades. If a dispute
should arise between the pad contractors and separate contractors
as to their responsibility for cleaning up the project site, McCarthy
Building Co. may clean up the site and charge the cost against the
contract amount of the pad contractors responsible as McCarthy Building
Co. determines to be just.
|
|
|
|
|
|
|
|
17.
|
SECURITY:
|
|
|
|
|
|
|
|
|
The
pad contractor is responsible for all temporary security or facilities
the pad contractor believes is required.
|
|
|
|
|
|
|
|
18.
|
HELICOPTER
LIFTS:
|
|
|
|
|
|
|
|
|
Helicopter
lifts should not be required on this project. If required,
the following standards shall apply:
|
|
|
|
|
|
|
|
|
|
a)
Lifts must be coordinated with McCarthy Building Co. two (2) weeks
in advance. |
|
|
|
|
b) Helicopter cranes shall be expected to comply with any applicable
regulations of the Federal Aviation Administration, O.S.H.A. and
local and state governing authorities. |
|
|
|
|
c) Helicopter lifts may not interfere with base building construction
or site work and must occur after normal working hours. Weekend
lifts are possible and Sunday is the day preferred by McCarthy Building
Co. |